Client: Town Hall
Location: London
Project Value: Circa £170k
Programme: 13 weeks
Project Management
Health and Safety
Handover Documentation
We were assigned a project at a hotel, which primarily involved builders' work on 10 apartments and suites. This included the removal and reinstatement of plasterboard ceilings and additional floor repairs. The project also encompassed alterations to bathroom plumbing and sanitaryware.
Since the hotel remained operational during our work, our team needed to be meticulous in setting up site and ensuring all hotels areas were protected from damage. We kept tools and equipment out of sight of guests and eliminated any trip hazards. Our main goal was to complete the work within the timeframe without affecting the guests or staff.