Celltarga were appointed as the principle contractor for the Reception upgrade works

Project Management 

Health and Safety

Handover Documentation

Client: British Broadcasting Corporation

Project Location: London

Project Sector: Office

Project Programme: 6 weeks

Celltarga were appointed as the principle contractor for the Reception upgrade works at an office in London, which involved a new reception desk, new public café bar area, bag scanner, and feature lighting. We worked with the appointed architect to develop the concept plans and provide contractors design for the bespoke joinery items and feature lighting scheme.

The project took place within a live reception environment over 2 phases so to enable to client to continue running normal operations. Phase 1 involved the installation of a new café bar which included a bespoke worktop and cabinetry set up, recycled plastic worktop, floating shelves, tiling, with associated M&E works to facilitate coffee machines and chilled water outlets.

 

Phase 2 was the installation of the new bespoke reception desk, with matching finishes to the café bar. Throughout these works, a temporary reception desk was provided for the client to use in order to maintain their operations and security throughout the works.

In addition, Celltarga partnered with a specialist signage contractor to install bespoke feature lighting above the café bar, and at high level in the atrium.